Sidewalk & Pathway Improvements

PPI-_5-landscapeedit.jpg

Pathway Improvements
Location: Burton St and Spaulding Ave
Estimated Completion: Week of 6/10/24
Funding Source: Pathways Fund

Repaving of the Burton St and Spaulding Ave stretches of pathway was completed 5/22/24.  The contractor will be on-site the week of 5/27/24 to place ADA-compliant concrete sidewalk ramps.  Restoration of topsoil and grass seed is scheduled to follow the week of 6/3/24.  Traffic control devices should be removed and the pathways formally reopened the week of 6/10/24.
 
Cascade Village Sidewalk Repair
Location: Various cracks and trip hazards in the Village District
Estimated Completion: 5/30/24
Funding Source: 50% DDA and 50% Township General Fund

Update 5/29/24: All concrete was successfully placed as of 5/21/24.  The contractor has completed a majority of the restoration and touchups should be completed 5/20/24.  The sidewalk is now open for public use.